The persistent water shortage across parts of Jos and Bukuru metropolis has been attributed to ageing infrastructure and ongoing rehabilitation of major water treatment facilities, with some installations operating for about 45 years without significant overhaul.

The Jos Water Services Corporation says the rehabilitation works are aimed at addressing longstanding infrastructure challenges and improving water production and distribution across the Plateau State capital.
Managing Director of the Corporation, Engr. Apollos Simon Samchi, disclosed this during an inspection tour of major water facilities with journalists today 23rd November 2026, including the Yakubu Gowon Dam and Water Treatment Plant at Ratt, Barkin Ladi, Lamingo Water Treatment Plant, Liberty Dam and British American Water Treatment Plant.
Samchi explained that the Plateau State Government, in partnership with the French Development Agency (AFD), had embarked on a comprehensive water supply improvement programme following an assessment that revealed the deteriorating condition of major water infrastructure.

He said the Yakubu Gowon Water Treatment Plant, one of the major facilities supplying water to Jos and Bukuru, had operated for approximately 45 to 50 years without significant rehabilitation, making a comprehensive overhaul necessary.
The project, valued at approximately €42 million, covers the rehabilitation of major treatment facilities, replacement of pumping equipment and expansion of pipeline networks, with an initial completion target of 18 months.
Samchi disclosed that civil engineering works at the Yakubu Gowon and Lamingo treatment plants had reached between 70 and 75 per cent completion, while pipeline extension works were approximately 40 per cent completed.
He said water production, which was below 30 per cent of the facilities’ capacity before the rehabilitation commenced, was expected to increase to at least 80 per cent upon completion.
However, he acknowledged that the ongoing rehabilitation works had temporarily affected water production and contributed to the shortage experienced by residents.
To mitigate the impact, Samchi identified the Yelwa Water Treatment Plant in Bukuru and the Nabor Water Treatment Plant around Nasarawa as some of the functional facilities currently supporting water distribution across parts of the metropolis.
He also encouraged residents to utilise the Corporation’s water tanker supply arrangements while the rehabilitation works continue.
The Resident Electrical and Mechanical Engineering Specialist on the project, Engr. Abdulhakim Busari, attributed the reduced production at the Yakubu Gowon facility to the poor condition of its pumping equipment and the shutdown of one of its operational phases for rehabilitation.
Busari explained that the plant operates in two phases, but Phase Two had been shut down to allow rehabilitation works, while Phase One was operating with only one functional pump instead of the three required.
He disclosed that six new pumps had been ordered and were expected to be shipped to Nigeria, adding that the equipment was specially designed to meet the city’s population requirements, water pressure and elevation challenges across distribution points.
According to him, the rehabilitation of Phase Two is expected to restore about 50 per cent of the plant’s production capacity by the first quarter of 2027, after which attention would shift to the complete rehabilitation of the other phase.
Busari said a two-week work programme had been introduced to monitor contractors’ activities, establish short-term targets and ensure the project meets its agreed 18-month completion schedule.
Engineer Zhengliang a foreign technical expert on site also assured that some of the equipment where already arriving in the country and installation will start as soon as they arrive site. He assured that the equipment where of high standards meeting specifications to resolve the technical overhaul of the water equipment.
The Corporation expressed optimism that the completion of the rehabilitation and pipeline extension projects would significantly improve water production and distribution across Jos and Bukuru metropolis, addressing longstanding challenges in access to potable water.